1 00:00:02,180 --> 00:00:11,740 [Music] 2 00:00:17,720 --> 00:00:14,959 Saturn 1b quarterly film report number 3 00:00:23,359 --> 00:00:17,730 27 covers progress during the period 4 00:00:25,550 --> 00:00:23,369 January February March 1966 during this 5 00:00:26,779 --> 00:00:25,560 quarter with a successful launch of the 6 00:00:30,710 --> 00:00:26,789 first Saturn 1b 7 00:00:32,389 --> 00:00:30,720 a s 201 the Saturn 1b program moved from 8 00:00:36,680 --> 00:00:32,399 a year of intensive launch vehicle 9 00:00:38,750 --> 00:00:36,690 ground testing to flight testing in 10 00:00:42,229 --> 00:00:38,760 early January the launch escape system 11 00:00:44,569 --> 00:00:42,239 for a s 201 was erected atop the Apollo 12 00:00:47,959 --> 00:00:44,579 spacecraft completing erection of the 13 00:00:51,229 --> 00:00:47,969 space vehicle on launch complex 34 Cape 14 00:00:53,630 --> 00:00:51,239 Kennedy pre-flight check out of the 15 00:00:57,439 --> 00:00:53,640 vehicle started last quarter continued 16 00:00:59,150 --> 00:00:57,449 as planned concurrently Marshalls 17 00:01:01,760 --> 00:00:59,160 contractors were completing the final 18 00:01:04,219 --> 00:01:01,770 phases of qualification testing of the 19 00:01:06,500 --> 00:01:04,229 flight components in some instances 20 00:01:09,800 --> 00:01:06,510 Marshall granted component qualification 21 00:01:13,850 --> 00:01:09,810 waivers for SI 201 based on previous 22 00:01:16,219 --> 00:01:13,860 thorough testing during early February 23 00:01:17,929 --> 00:01:16,229 several technical meetings were held to 24 00:01:20,570 --> 00:01:17,939 evaluate the data from the various 25 00:01:22,999 --> 00:01:20,580 pre-launch tests including the space 26 00:01:26,840 --> 00:01:23,009 vehicle countdown demonstration test and 27 00:01:29,030 --> 00:01:26,850 the flight readiness test following two 28 00:01:31,490 --> 00:01:29,040 postponements caused by unfavorable 29 00:01:34,039 --> 00:01:31,500 weather final launch preparations were 30 00:01:36,469 --> 00:01:34,049 begun this final countdown was 31 00:01:38,990 --> 00:01:36,479 interrupted by two launch vehicle holds 32 00:01:47,260 --> 00:01:39,000 both because of low pressure in the 33 00:01:54,200 --> 00:01:50,480 liftoff of the unmanned vehicle occurred 34 00:01:55,630 --> 00:01:54,210 on February 26th at 11:12 a.m. Eastern 35 00:01:58,760 --> 00:01:55,640 Standard Time 36 00:02:00,620 --> 00:01:58,770 this liftoff marked the first use of a 37 00:02:04,100 --> 00:02:00,630 new flight testing procedure for the 38 00:02:06,139 --> 00:02:04,110 Saturn program the all-up concept where 39 00:02:08,779 --> 00:02:06,149 all stages and modules of the first 40 00:02:12,920 --> 00:02:08,789 flight vehicle are live or functioning 41 00:02:13,910 --> 00:02:12,930 units the Chrysler built and the eight 42 00:02:16,070 --> 00:02:13,920 Rocketdyne 43 00:02:19,100 --> 00:02:16,080 h-1 engines performed well within 44 00:02:21,800 --> 00:02:19,110 tolerances the pressure of the gaseous 45 00:02:26,900 --> 00:02:21,810 nitrogen control pressure sphere was as 46 00:02:29,600 --> 00:02:26,910 planned during flight at t-plus 141 47 00:02:32,090 --> 00:02:29,610 seconds the for inboard engines cut-off 48 00:02:37,479 --> 00:02:32,100 followed six seconds later by the 49 00:02:39,830 --> 00:02:37,489 outboard engines within a few seconds 50 00:02:42,140 --> 00:02:39,840 successful stage separation had been 51 00:02:44,750 --> 00:02:42,150 achieved and the second stage engine 52 00:02:47,449 --> 00:02:44,760 ignited as shown by a camera mounted in 53 00:02:49,430 --> 00:02:47,459 the first stage separation disturbances 54 00:02:52,850 --> 00:02:49,440 were quite small with the first stage 55 00:02:55,039 --> 00:02:52,860 being very stable the Douglas built 56 00:02:57,590 --> 00:02:55,049 second stages overall performance was 57 00:03:00,470 --> 00:02:57,600 excellent this was the first flight test 58 00:03:02,780 --> 00:03:00,480 of the stage and it's j2 engine the 59 00:03:04,970 --> 00:03:02,790 engine built by Rocketdyne is the most 60 00:03:08,870 --> 00:03:04,980 powerful liquid hydrogen engine being 61 00:03:10,850 --> 00:03:08,880 manufactured after about 20 seconds of 62 00:03:13,580 --> 00:03:10,860 second stage burning the launch escape 63 00:03:17,780 --> 00:03:13,590 tower of the 46 thousand pound Apollo 64 00:03:20,870 --> 00:03:17,790 spacecraft was jettisoned the instrument 65 00:03:22,970 --> 00:03:20,880 unit built by IBM performed precisely as 66 00:03:25,729 --> 00:03:22,980 designed commanding the flight of the 67 00:03:27,500 --> 00:03:25,739 vehicle through payload separation this 68 00:03:29,750 --> 00:03:27,510 was also the first flight test of the 69 00:03:32,000 --> 00:03:29,760 instrument unit which like the second 70 00:03:36,590 --> 00:03:32,010 stage will be used with the saturn v 71 00:03:38,990 --> 00:03:36,600 launch vehicle ten minutes after liftoff 72 00:03:42,289 --> 00:03:39,000 the second stage engine had completed 73 00:03:44,360 --> 00:03:42,299 its job and shut down at this point the 74 00:03:45,229 --> 00:03:44,370 Apollo spacecraft was a hundred sixty 75 00:03:47,240 --> 00:03:45,239 miles high 76 00:03:51,050 --> 00:03:47,250 traveling over fifteen thousand miles 77 00:03:53,960 --> 00:03:51,060 per hour after reaching an Apogee of 78 00:03:55,280 --> 00:03:53,970 about 300 miles the spacecraft was 79 00:03:58,370 --> 00:03:55,290 propelled back into the Earth's 80 00:04:00,500 --> 00:03:58,380 atmosphere by a service module engine to 81 00:04:03,979 --> 00:04:00,510 provide an extreme test for the command 82 00:04:06,440 --> 00:04:03,989 modules heat shield the command module 83 00:04:08,330 --> 00:04:06,450 was recovered in the South Atlantic by 84 00:04:11,840 --> 00:04:08,340 Department of Defense recovery forces 85 00:04:14,120 --> 00:04:11,850 and returned for detailed study the 86 00:04:16,460 --> 00:04:14,130 complete success of a s 201 in 87 00:04:18,529 --> 00:04:16,470 performing its prime missions which 88 00:04:21,199 --> 00:04:18,539 included verifying spacecraft and launch 89 00:04:24,020 --> 00:04:21,209 vehicle compatibility and launch vehicle 90 00:04:26,029 --> 00:04:24,030 structural integrity provided NASA with 91 00:04:27,680 --> 00:04:26,039 increased confidence in meeting its 92 00:04:32,930 --> 00:04:27,690 manned space exploration 93 00:04:36,080 --> 00:04:32,940 goals as planned AAS 203 now scheduled 94 00:04:38,450 --> 00:04:36,090 for launch before a s 202 will not carry 95 00:04:40,970 --> 00:04:38,460 an Apollo spacecraft but rather a 96 00:04:43,580 --> 00:04:40,980 lightweight nose cone this will allow 97 00:04:46,160 --> 00:04:43,590 the s4b to go into orbit with about ten 98 00:04:48,680 --> 00:04:46,170 tons of liquid hydrogen aboard during 99 00:04:50,810 --> 00:04:48,690 the three orbit mission the dynamics of 100 00:04:53,060 --> 00:04:50,820 liquid hydrogen in space will be studied 101 00:04:55,060 --> 00:04:53,070 to gain additional data on the behavior 102 00:04:57,890 --> 00:04:55,070 of this fuel under weightless conditions 103 00:05:00,490 --> 00:04:57,900 such information is needed to perfect 104 00:05:10,180 --> 00:05:00,500 the restart of the s4b in Earth orbit 105 00:05:15,860 --> 00:05:13,700 booster post static check out for sa 203 106 00:05:18,100 --> 00:05:15,870 was completed at Marshalls Mishu 107 00:05:20,330 --> 00:05:18,110 assembly facility in early March 108 00:05:23,150 --> 00:05:20,340 preparations for stage shipment are in 109 00:05:26,690 --> 00:05:23,160 process shipment to the Cape is planned 110 00:05:28,490 --> 00:05:26,700 for early April on the west coast 111 00:05:31,640 --> 00:05:28,500 Douglas efforts centered around the 112 00:05:33,770 --> 00:05:31,650 second stage for sa 203 do two part 113 00:05:35,990 --> 00:05:33,780 shortages pre accept inspiring 114 00:05:38,780 --> 00:05:36,000 activities proceeded slowly until the 115 00:05:41,540 --> 00:05:38,790 first week in February stage power on 116 00:05:43,880 --> 00:05:41,550 check out an LH to experiment TV system 117 00:05:47,060 --> 00:05:43,890 manual checkout was completed by mid 118 00:05:49,460 --> 00:05:47,070 quarter in late February to acceptance 119 00:05:51,320 --> 00:05:49,470 firings were aborted due to malfunctions 120 00:05:53,960 --> 00:05:51,330 in the automatic firing sequence tapes 121 00:05:58,220 --> 00:05:53,970 and a small fire in the engine fuel pump 122 00:06:00,680 --> 00:05:58,230 area on February 26th a 289 second 123 00:06:02,990 --> 00:06:00,690 acceptance firing - LOX depletion was 124 00:06:06,730 --> 00:06:03,000 successfully completed shipment to the 125 00:06:11,300 --> 00:06:09,710 meanwhile installation of components in 126 00:06:13,700 --> 00:06:11,310 the instrument unit for the second 127 00:06:16,330 --> 00:06:13,710 flight vehicle was completed on February 128 00:06:18,710 --> 00:06:16,340 23rd and check-out began the next day 129 00:06:22,070 --> 00:06:18,720 unit checkout continued throughout the 130 00:06:25,520 --> 00:06:22,080 quarter shipment to KSC is planned for 131 00:06:27,409 --> 00:06:25,530 next quarter preparation for shipping 132 00:06:29,840 --> 00:06:27,419 the lightweight nose cone was completed 133 00:06:32,480 --> 00:06:29,850 in February the nose cone departed 134 00:06:36,740 --> 00:06:32,490 Marshall March first and arrived at KSC 135 00:06:38,690 --> 00:06:36,750 ten days later following post static 136 00:06:41,159 --> 00:06:38,700 check out the booster for the third 137 00:06:42,719 --> 00:06:41,169 flight vehicle sa 202 138 00:06:44,999 --> 00:06:42,729 was shipped from Chrysler's musci 139 00:06:45,600 --> 00:06:45,009 assembly facility to the Cape February 140 00:06:48,450 --> 00:06:45,610 7th 141 00:06:50,850 --> 00:06:48,460 immediately after launch complex 34 pad 142 00:06:55,439 --> 00:06:50,860 refurbishment the stage was erected on 143 00:06:57,420 --> 00:06:55,449 March 4th at Douglass's sacto facility 144 00:07:00,600 --> 00:06:57,430 post static checkout of the second stage 145 00:07:02,519 --> 00:07:00,610 was completed January 6th the stage was 146 00:07:05,369 --> 00:07:02,529 shipped from sacto by ocean vessel 147 00:07:06,749 --> 00:07:05,379 January 15 and was offloaded at the Cape 148 00:07:08,610 --> 00:07:06,759 January 29th 149 00:07:10,439 --> 00:07:08,620 it was then moved to the vertical 150 00:07:13,050 --> 00:07:10,449 Assembly Building for inspection and 151 00:07:17,129 --> 00:07:13,060 storage the stage was stacked atop the 152 00:07:19,499 --> 00:07:17,139 booster March 9th at IBM Huntsville 153 00:07:22,320 --> 00:07:19,509 instrument unit checkout was completed 154 00:07:24,890 --> 00:07:22,330 on February 4th the unit was barged to 155 00:07:27,749 --> 00:07:24,900 the Cape arriving February 21st 156 00:07:30,329 --> 00:07:27,759 following pre erection activities it was 157 00:07:32,550 --> 00:07:30,339 stacked atop the second stage March 11th 158 00:07:36,300 --> 00:07:32,560 preflight check out of the entire launch 159 00:07:38,640 --> 00:07:36,310 vehicle is underway at the Marshall 160 00:07:40,649 --> 00:07:38,650 systems development facility development 161 00:07:43,260 --> 00:07:40,659 and verification of the computer program 162 00:07:46,529 --> 00:07:43,270 tapes for automatic check out of ese 202 163 00:07:49,050 --> 00:07:46,539 was completed in March at the end of 164 00:08:00,179 --> 00:07:49,060 March the facility was being updated to 165 00:08:01,829 --> 00:08:00,189 the ese 203 configuration at Marshall 166 00:08:03,929 --> 00:08:01,839 the booster for the fourth flight 167 00:08:07,110 --> 00:08:03,939 vehicle underwent two successful static 168 00:08:14,309 --> 00:08:07,120 firings the first on January 17th the 169 00:08:17,100 --> 00:08:14,319 second on January 21st the booster was 170 00:08:19,709 --> 00:08:17,110 shipped from Marshall January 28th ten 171 00:08:21,889 --> 00:08:19,719 days ahead of schedule adverse weather 172 00:08:24,989 --> 00:08:21,899 and river conditions at Cairo Illinois 173 00:08:27,929 --> 00:08:24,999 prevented further safe transit the pole 174 00:08:30,239 --> 00:08:27,939 Amon returned to MSFC February 9th and 175 00:08:32,639 --> 00:08:30,249 loaded the instrument unit for the third 176 00:08:35,279 --> 00:08:32,649 flight vehicle for simultaneous River 177 00:08:37,740 --> 00:08:35,289 shipment to miss you the barge departed 178 00:08:42,300 --> 00:08:37,750 the center February 11 and arrived at 179 00:08:44,430 --> 00:08:42,310 MAF February 16th the stage was 180 00:08:46,769 --> 00:08:44,440 subsequently offloaded then moved to the 181 00:08:49,230 --> 00:08:46,779 assembly facility where post static 182 00:08:51,360 --> 00:08:49,240 checkout began March 31st ahead of 183 00:08:53,370 --> 00:08:51,370 schedule the instrument unit was 184 00:08:54,400 --> 00:08:53,380 transshipped to the barge promise for 185 00:08:57,670 --> 00:08:54,410 shipment to the 186 00:08:59,350 --> 00:08:57,680 a prosthetic check out for the fifth 187 00:09:00,309 --> 00:08:59,360 flight booster was completed in early 188 00:09:02,009 --> 00:09:00,319 January 189 00:09:05,769 --> 00:09:02,019 it was then prepared for shipment 190 00:09:10,180 --> 00:09:05,779 departing Mishu February 17 and arriving 191 00:09:12,069 --> 00:09:10,190 at Marshall February 26 the stage was 192 00:09:14,319 --> 00:09:12,079 immediately installed in the static test 193 00:09:16,869 --> 00:09:14,329 stand and Chrysler prepared the stage 194 00:09:19,300 --> 00:09:16,879 for acceptance firing the stage was 195 00:09:21,490 --> 00:09:19,310 fired March 23rd and March 31st as 196 00:09:25,329 --> 00:09:21,500 scheduled the stage is now being 197 00:09:27,249 --> 00:09:25,339 prepared for shipment to miss Yu stage 198 00:09:29,259 --> 00:09:27,259 assembly of the six flight booster was 199 00:09:31,540 --> 00:09:29,269 completed this quarter pre static 200 00:09:33,460 --> 00:09:31,550 checkout got underway immediately and is 201 00:09:37,179 --> 00:09:33,470 scheduled for completion early next 202 00:09:38,769 --> 00:09:37,189 quarter Assembly of the first stage for 203 00:09:40,990 --> 00:09:38,779 the seventh flight vehicle started 204 00:09:44,889 --> 00:09:41,000 February 2nd and is scheduled for 205 00:09:46,480 --> 00:09:44,899 completion next quarter fabrication of 206 00:09:48,460 --> 00:09:46,490 the eighth flight booster continued 207 00:09:51,720 --> 00:09:48,470 throughout the quarter and fabrication 208 00:09:54,009 --> 00:09:51,730 of the ninth flight booster got underway 209 00:09:56,350 --> 00:09:54,019 Chrysler continued with component 210 00:10:04,550 --> 00:09:56,360 qualification testing of s1b units 211 00:10:09,290 --> 00:10:07,179 at Douglass's Huntington Beach facility 212 00:10:11,420 --> 00:10:09,300 inspection and installation of 213 00:10:12,829 --> 00:10:11,430 components in the lh2 tank for the 214 00:10:15,259 --> 00:10:12,839 second stage of the fourth flight 215 00:10:18,410 --> 00:10:15,269 vehicle were completed in early January 216 00:10:20,389 --> 00:10:18,420 On January 10th the stage was shipped 217 00:10:23,840 --> 00:10:20,399 aboard the Orion from Seal Beach 218 00:10:26,030 --> 00:10:23,850 arriving at SAC tow January 14th it was 219 00:10:28,910 --> 00:10:26,040 installed in beta 3 tests and upon 220 00:10:30,920 --> 00:10:28,920 arrival following receiving inspection 221 00:10:33,319 --> 00:10:30,930 and modification and installation of 222 00:10:37,309 --> 00:10:33,329 late parts pre static checks began 223 00:10:39,319 --> 00:10:37,319 January 24th on March 18th Douglas 224 00:10:41,600 --> 00:10:39,329 successfully acceptance fired the stage 225 00:10:43,819 --> 00:10:41,610 on the first attempt the stage is now 226 00:10:47,329 --> 00:10:43,829 expected to be ready for delivery well 227 00:10:50,660 --> 00:10:47,339 ahead of schedule back to recheck out 228 00:10:52,850 --> 00:10:50,670 for s4b 205 shown at right started this 229 00:10:54,559 --> 00:10:52,860 quarter at Douglas parts shortages 230 00:10:57,350 --> 00:10:54,569 temporarily delayed completion of 231 00:10:59,360 --> 00:10:57,360 checkout until March 22nd following 232 00:11:03,650 --> 00:10:59,370 final inspections it will be shipped to 233 00:11:05,329 --> 00:11:03,660 sacto next quarter insulating the second 234 00:11:07,819 --> 00:11:05,339 stage of the six flight vehicle was 235 00:11:09,860 --> 00:11:07,829 completed in January miscellaneous 236 00:11:12,410 --> 00:11:09,870 horizontal installations cleaning of the 237 00:11:14,170 --> 00:11:12,420 lh2 tank joining the thrust structure 238 00:11:16,549 --> 00:11:14,180 and forward and aft skirts and 239 00:11:18,920 --> 00:11:16,559 installation of the engine were also 240 00:11:23,090 --> 00:11:18,930 completed this quarter factory checkout 241 00:11:25,309 --> 00:11:23,100 is underway joining the forward LH to 242 00:11:27,410 --> 00:11:25,319 dome to the LH to tank for the second 243 00:11:30,079 --> 00:11:27,420 stage of the seventh flight vehicle was 244 00:11:32,269 --> 00:11:30,089 completed in January the stage was then 245 00:11:35,210 --> 00:11:32,279 subjected to hydrostatic pneumatic leak 246 00:11:37,429 --> 00:11:35,220 and dive tests in February installation 247 00:11:40,400 --> 00:11:37,439 of stage insulation was completed March 248 00:11:44,389 --> 00:11:40,410 10 components are now being installed in 249 00:11:46,340 --> 00:11:44,399 the stage the LOX tank and forward lh2 250 00:11:48,889 --> 00:11:46,350 dome for the second stage of the 8th 251 00:11:50,809 --> 00:11:48,899 launch vehicle were shipped from da C's 252 00:11:53,449 --> 00:11:50,819 Santa Monica facility to Huntington 253 00:11:54,829 --> 00:11:53,459 Beach early this quarter stage assembly 254 00:11:57,350 --> 00:11:54,839 progressed at Huntington Beach 255 00:11:59,150 --> 00:11:57,360 throughout the quarter hydrostatic proof 256 00:12:01,790 --> 00:11:59,160 testing of the tanks is scheduled to 257 00:12:03,650 --> 00:12:01,800 begin next quarter fabrication of the 258 00:12:08,059 --> 00:12:03,660 stages for the 9th and 10th launch 259 00:12:10,040 --> 00:12:08,069 vehicles was begun Douglas continued s4b 260 00:12:12,679 --> 00:12:10,050 qualification testing this period 261 00:12:14,949 --> 00:12:12,689 testing of the s4 be common bulkhead 262 00:12:17,689 --> 00:12:14,959 test specimen under cryogenic conditions 263 00:12:19,210 --> 00:12:17,699 started last quarter was completed in 264 00:12:21,800 --> 00:12:19,220 early Jan 265 00:12:24,140 --> 00:12:21,810 although the specimen failed during the 266 00:12:27,200 --> 00:12:24,150 latter test phases data from this test 267 00:12:30,770 --> 00:12:27,210 program indicated no problem existed for 268 00:12:33,050 --> 00:12:30,780 the flight stages other qualification 269 00:12:35,120 --> 00:12:33,060 testing included vibration thermal shock 270 00:12:37,910 --> 00:12:35,130 and functional testing of the s4 bees 271 00:12:41,390 --> 00:12:37,920 main fuel feed duct at Douglass's Santa 272 00:12:43,850 --> 00:12:41,400 Monica facility and testing of the s4 B 273 00:12:53,030 --> 00:12:43,860 oxidizer duct assembly at wiley 274 00:12:55,160 --> 00:12:53,040 laboratory El Segundo California at 275 00:12:57,200 --> 00:12:55,170 Marshall structural testing of the 276 00:12:59,780 --> 00:12:57,210 second structural test instrument unit 277 00:13:02,360 --> 00:12:59,790 begun December 30th was completed this 278 00:13:07,010 --> 00:13:02,370 quarter following a series of successful 279 00:13:08,900 --> 00:13:07,020 tests the unit failed February 2nd the 280 00:13:12,170 --> 00:13:08,910 IU was later broken down into sections 281 00:13:13,820 --> 00:13:12,180 for post test examination evaluation of 282 00:13:15,440 --> 00:13:13,830 all test data indicated that the 283 00:13:19,750 --> 00:13:15,450 instrument unit structure is fully 284 00:13:21,830 --> 00:13:19,760 qualified for manned Saturn 1b vehicles 285 00:13:23,540 --> 00:13:21,840 component installation in the fourth 286 00:13:25,280 --> 00:13:23,550 flight instrument unit continued 287 00:13:28,940 --> 00:13:25,290 throughout the period with completion 288 00:13:30,680 --> 00:13:28,950 planned for next quarter structural 289 00:13:32,840 --> 00:13:30,690 segments for the next instrument unit 290 00:13:34,540 --> 00:13:32,850 were received this quarter assembly 291 00:13:44,840 --> 00:13:34,550 started March fifth component 292 00:13:47,930 --> 00:13:44,850 installation will start next quarter at 293 00:13:50,450 --> 00:13:47,940 rocket Dynes Santa Susana facility j2 294 00:13:52,220 --> 00:13:50,460 engine qualification service life tests 295 00:13:54,650 --> 00:13:52,230 were conducted in early January the 296 00:13:59,990 --> 00:13:54,660 engine was subjected to seven successive 297 00:14:02,420 --> 00:14:00,000 full duration 502nd firings at Canoga 298 00:14:04,220 --> 00:14:02,430 Park a new facility an electrical 299 00:14:06,830 --> 00:14:04,230 assembly cleanroom production line has 300 00:14:08,570 --> 00:14:06,840 been placed in operation it will be used 301 00:14:17,890 --> 00:14:08,580 in the buildup of electrical control 302 00:14:22,820 --> 00:14:20,480 delivery of electrical ground support 303 00:14:25,460 --> 00:14:22,830 equipment from general electrics Daytona 304 00:14:27,800 --> 00:14:25,470 fabrication facility to KSC was 305 00:14:29,450 --> 00:14:27,810 completed at the end of February this 306 00:14:32,870 --> 00:14:29,460 equipment has been installed at launch 307 00:14:35,360 --> 00:14:32,880 complex 37b the second of two Saturn 1b 308 00:14:39,650 --> 00:14:35,370 launch complexes check out of this 309 00:14:41,330 --> 00:14:39,660 equipment is in progress during March in 310 00:14:44,090 --> 00:14:41,340 connection with the super guppy flight 311 00:14:46,580 --> 00:14:44,100 test program a ground test second stage 312 00:14:50,300 --> 00:14:46,590 was successfully flown in the guffy from 313 00:14:52,880 --> 00:14:50,310 Huntsville to California at Marshalls 314 00:14:56,330 --> 00:14:52,890 auxiliary propulsion system facility an 315 00:14:58,940 --> 00:14:56,340 ApS module was tested on January 26th in 316 00:15:01,250 --> 00:14:58,950 the altitude test cell to check out 317 00:15:03,320 --> 00:15:01,260 compatibility of the module and facility 318 00:15:06,400 --> 00:15:03,330 this was the first in a series of 319 00:15:09,800 --> 00:15:06,410 altitude tests using the complete system 320 00:15:12,230 --> 00:15:09,810 in summary January February and March 321 00:15:14,210 --> 00:15:12,240 were months of notable achievements and 322 00:15:16,910 --> 00:15:14,220 on schedule deliveries within the Saturn 323 00:15:19,990 --> 00:15:16,920 1b program including the orderly build 324 00:15:22,490 --> 00:15:20,000 up of Saturn 1b stages and equipment 325 00:15:25,940 --> 00:15:22,500 delivery of ground support equipment to 326 00:15:29,720 --> 00:15:25,950 Launch Complex 37 be increased load 327 00:15:32,090 --> 00:15:29,730 capacity in air freight service and the 328 00:15:34,230 --> 00:15:32,100 spectacular and highly successful flight